Prepare for UPSC Indian Engineering Services (IES/ESE) with official previous years' questions, detailed derivations, IS Code references, and step-by-step structural calculations across Structural Analysis, Soil Mechanics & Foundation Engineering, Fluid Mechanics & Hydraulics, RCC & Steel Structures, Surveying, Environmental Engineering, and Transportation.
Marking pattern: +2.00 positive, -0.66 negative (Official UPSC ESE 1/3rd Negative Marking Scheme; 150 Questions, 300 Marks).
A fixed-fixed beam '$AB$' of length $3\text{ m}$ is subjected to a point load of $45\text{ kN}$ at a distance $2\text{ m}$ from left support '$A$'. What are the vertical reaction forces at both the supports '$A$' and '$B$'?
A cantilever wooden beam is $3\text{ m}$ long and carries a UDL of $4\text{ kN/m}$. The cross-section of the beam is $100\text{ mm}$ width and $200\text{ mm}$ depth. What is the maximum bending stress for this section?
In the context of measures of surfaces, which one of the following is not correct?
A hollow steel column carrying an axial load of $2.1\text{ MN}$ has an ultimate stress of $510\text{ N/mm}^2$. The internal diameter of the column is $150\text{ mm}$. Consider the factor of safety as $4$. What is the external diameter of the column?
The tensile stresses at a point across two mutually perpendicular planes are $150\text{ N/mm}^2$ and $80\text{ N/mm}^2$. What are the normal and tangential stresses, respectively, on a plane inclined at $30^{\circ}$ to the axis of the minor stress?
The angle made by the resultant stress with the normal of the oblique plane is known as obliquity ($\phi$) and is expressed as:
A central load of $2500\text{ N}$ is acting on a leaf spring. The leaf spring is to be made of $12$ steel plates of $6\text{ cm}$ width and $5\text{ mm}$ thickness. If the bending stress is limited to $200\text{ N/mm}^2$, then the length and deflection at the centre of the spring are, respectively: (Assume Modulus of elasticity as $2 \times 10^5\text{ N/mm}^2$)
A $150\text{ N}$ load is acting on a close coiled helical spring. The mean coil diameter has to be $12$ times that of the wire diameter. If the maximum shear stress is not to exceed $150\text{ N/mm}^2$, what is the diameter of the coil ?
A circular rod of $20\text{ mm}$ diameter and $400\text{ mm}$ length is subjected to a tensile force of $50\text{ kN}$. What is the volumetric strain, if Poisson's ratio $= 0.25$ and Young's modulus $E = 2 \times 10^5\text{ N/mm}^2$ ?
A rod which tapers uniformly from $30\text{ mm}$ diameter to $15\text{ mm}$ diameter in a length of $300\text{ mm}$ is subjected to an axial load of $6\text{ kN}$. If Young's modulus is $2 \times 10^5\text{ N/mm}^2$, what is the elongation of the rod ?
Which one of the following is a measure of the ability of a material to absorb energy before fracture?
A $10$ coils $120\text{ mm}$ mean diameter closely coiled helical spring is made up of a $12\text{ mm}$ steel wire. If the spring is carrying an axial load of $150\text{ N}$, what is the maximum shear stress? (Take modulus of rigidity $C = 8.16 \times 10^4\text{ N/mm}^2$)
The optimistic time estimate is defined as :
What is the expected time of completion of an activity, if the optimistic time ($t_o$) is $4\text{ days}$, most likely time ($t_L$) is $6\text{ days}$ and pessimistic time ($t_P$) is $11\text{ days}$?
Independent float is defined as:
The details of marks of the technical and the financial bids of four bidders, who bid for a project having an estimated cost of $\text{INR } 1,00,000$ are given as follows :
| Contractor | Score of Technical Bid | Financial Bid (INR) |
|---|---|---|
| A | 80 | 1,35,000 |
| B | 75 | 1,25,000 |
| C | 45 | 1,01,000 |
| D | 60 | 1,15,000 |
To whom can the contract be awarded with the following conditions :
Choose the correct answer from the options given below :
A construction firm is considering to execute a structural modification project in a running manufacturing mill. Due to technical reasons, the work is to be executed slowly and carefully. It is expected that only $20\text{ tons}$ of fabrication is possible in each month. The firm has an estimated fixed cost (equipment, supervision, overhead deployment) of $\text{₹}1,50,000$ per month, variable cost (labour and material) of $\text{₹}30,000$ per month and $\text{₹}35,000$ for normal cost of fabrication. What is the rate that should be quoted by the firm to achieve at least $10\%$ profit?
A preliminary survey indicates that $20\%$ of the time of a gang of workers is spent idly. What is the total number of observations required to determine the proportion of idle time within $\pm 5\%$ with $95\%$ confidence limit? (Take $Z$ value as $2.0$)
Construction of a military helipad at an altitude of $2400\text{ m}$ involves $88000\text{ m}^3$ (loose) of excavation area in soft soil. This task needs to be completed in $200$ working hours. The company entrusted two dozers, each with an output of $220\text{ m}^3\text{/h}$ under job conditions for task execution. It also holds wheel loaders and $22\text{ m}^3$ dump trucks. One loader can load in trucks, about $120\text{ m}^3$ of excavated soil per hour. The dump truck cycle time for disposal of excavated materials is $40$ minutes. This includes $8$ minutes of loading time by a loader team that consists of $2$ loaders. In this case, the total number of dumpers required to complete the task on time is :
What is the amount of water required per hour for compacting loose soil being spread by a shovel and dozer at the rate of $230\text{ m}^3\text{/h}$ for a soil having density of $1.5\text{ t/m}^3$ and $8\%$ moisture content needing $12\%$ optimum moisture content for compaction?
What is the time required to grade and finish $30\text{ km}$ of road formation with width equal to thrice the width of the motor grader, using six passes of the motor grader with speed for each of the successive two passes as $6\text{ km/h}$, $8\text{ km/h}$ and $10\text{ km/h}$ respectively? (Take machine efficiency based on operator's skill, machine characteristics and working conditions as $75\%$)
Match the following lists:
| List-I | List-II |
|---|---|
| P. ISO 9001:2015 | 1. Guidelines for Quality Plans |
| Q. ISO 9004:2018 | 2. Requirements for Quality Management Systems |
| R. ISO 10005:2018 | 3. Guidelines for Quality Management in Projects |
| S. ISO 10006:2017 | 4. Guidelines to achieve Sustained Success |
Select the correct answer using the code given below:
| Option | P | Q | R | S |
|---|---|---|---|---|
| (a) | 2 | 4 | 1 | 3 |
| (b) | 4 | 2 | 1 | 3 |
| (c) | 1 | 2 | 4 | 3 |
| (d) | 3 | 1 | 2 | 4 |
For the following data, what is the rate of crashing?
Crash cost $= \text{INR } 10,000$
Normal cost $= \text{INR } 5,000$
Normal time $= 10\text{ days}$
Crash time $= 5\text{ days}$
Under time-related financial incentive schemes, the employee is paid :
Considering A and B as two activities of a project, what are the standard deviation of Activity A and B ?
| Activity A | Activity B |
|---|---|
| Optimistic time $(t_o) = 4\text{ days}$ | Optimistic time $(t_o) = 4\text{ days}$ |
| Most likely time $(t_L) = 6\text{ days}$ | Most likely time $(t_L) = 7\text{ days}$ |
| Pessimistic time $(t_P) = 16\text{ days}$ | Pessimistic time $(t_P) = 22\text{ days}$ |